- Home
- Departments
- Engineering
- West Main Street Improvements
West Main Street Improvements
Project Updates: May 26, 2023
West Main Updates from Prime Engineering:
The concrete curb and gutter crews completed the long sections remaining on the south side of W. Main Street this week. Full depth pavement removal is taking place in front of the gutter in preparation for full depth asphalt. Full depth asphalt should be completed next week prior to the Strawberry Festival.
The contractor will continue to work on the south side concrete ramps, sidewalks, and drive approaches now that the long sections of curb and gutter are in.
The north side streetscape is almost complete. Power washing and concrete sealing will be applied to the completed portions next week prior to the Festival, and are already underway. The remaining portion at N. Cherry Street will be done after the Troy Strawberry Festival so that walkways are safer for festival visitors.
Traffic signal and lighting crews will commence work as materials become available. These items have long lead times for production.
For more information, submit your question via email to: MainStImprovements@primeeng.com. Upcoming road closures can be viewed here.
Want to receive weekly updates about West Main Street? Sign up here.
Update Archive
May 26, 2023
May 11, 2023
April 21, 2023
April 6, 2023
March 27, 2023
March 17, 2023
March 7, 2023
February 14, 2023
January 24, 2023
January 6, 2023
December 20, 2022
December 13, 2022
November 14, 2022
November 7, 2022
October 24, 2022
October 17, 2022
October 10, 2022
September 30, 2022
September 23, 2022
September 1, 2022
August 26, 2022
Project Overview: A road to a better Troy!
Beginning in 2022, the City of Troy will make major improvements to Main Street (State Route 41), stretching from 1-75 to the Public Square. These improvements are intended to not only upgrade the existing infrastructure, but to improve traffic flow and safety for Troy's main through road.
The project will:
- Widen the roadway
- Replace sidewalk curb and gutter
- Provide a 4-foot grass strip between the roadway and the sidewalk along the corridor
- Modify the roadway between Adams Street and Cherry Street to provide three lanes and deeper angled parking stalls
- Install a raised median between Elm Street and Adams Street
- Remove stoplights at Cherry Street and Cedar Street, replacing them with a two-way north-south stop
- Relocate the stoplight from Monroe Street to Oxford Street
- Install advanced-detection signals at all stoplights in the corridor
- Upgrade lighting
- Upgrade buried infrastructure where applicable (including CenterPoint gas lines)
- Burying existing overhead electric and fiber utilities between Dorset Road and Ridge Avenue
Some of these improvements are illustrated below. Traffic studies show that over 20 percent of crashes in Troy occur on the West Main Corridor. Wider lanes mean less congestion, fewer incidences of sideswipe crashes, and safer pedestrians.
Public Presentation Phase 1
Public Presentation Phase 2
Phase 1 Proposed Plans
Phase 2 Proposed Plans
Timeline
Utility improvements began in spring 2022 along the West Main Street Corridor. Phase 1 of the project, stretching from Ridge Avenue to Cherry Street will begin in summer 2022. Phase 2 of the project, from the 1-75 on-ramp to Ridge Avenue will begin in fall 2023.
Proposed Improvements
Some of the proposed improvements are illustrated below.
Widened Roadways
A typical section of the new West Main Corridor will have wider lanes than currently exist, which will reduce sideswipe accidents.
Buffered Sidewalks
While the sidewalks along West Main will remain at five feet, a wider buffer strip will keep pedestrians away from traffic.
Traffic Flow Improvements
Several changes will be made to improve traffic flow along West Main. Some of these are illustrated below.
Phase 1 will include upgrades and changes to traffic signals from the downtown area to Ridge Avenue.
Phase 2 will bring updates to major intersections as described in the below graphic.
FAQs:
Will the corridor be more pedestrian friendly?
Yes! The current curbs are nonexistent in many locations around the corridor as well as the sidewalks are in need of replacement due to tripping hazards, cracking and pitting. After the project, a grass buffer will exist between the sidewalks and the road, making the sidewalks safer for pedestrians.
Will traffic congestion be reduced at the end of the project?
Yes. The addition of turn lanes (for example: at the Dorset Road intersection) will reduce unnecessary queuing, and smarter traffic signals will help to move traffic along. Some current traffic signals operate on a timer and do not "see" vehicles. The new traffic signals will include sensors that detect traffic at intersections and be able to adjust according to traffic volumes.
How is the project being funded?
The project is being funded from several different sources. The City obtained federal grant funding to improve the safety along the corridor, assistance from Ohio Department of Transportation for an urban paving program, and grant funding from Ohio Public Works Commission (OPWC) to improve the corridor. The project will be funded by City funds for the remainder of the project.
Are there any aesthetic elements included in the project?
The entire corridor is getting a new layer of asphalt, new curbs, sidewalks, traffic signals, street trees closer to downtown, street scape in front of the Miami County Courthouse, and many other aesthetic features. The corridor as a whole is receiving a “face lift.” A new curb lawn—the median between the sidewalk and the street—will create a cleaner look for our sidewalks. The City has worked diligently with AES in order to bury the power pole line along the corridor between Ridge Avenue and Dorset Road.
Where is the space for the widened road coming from?
To accommodate lane widening and the new median between the grass and the sidewalks, the City is widening the overall footprint of the corridor. The additional footage is included in the existing right-of-way, the area that is owned by the City.
Tips for Living with Construction
While construction can be annoying, it won’t last forever—and workers on the ground are building a better thoroughfare for our community. Please be kind to our workers, and plan ahead to make travelling easier.
- Postal mail about project in your area will come labeled with the City of Troy logo, so keep an eye out for envelopes marked with that logo.
- Please continue to support our local businesses! Driveways will remain open unless coordinated with property owners.
- Take construction into account when you’re planning drive times, and consider consolidating trips.
- Plan alternative routes. Visit our Road Closures map to plan detours. You can see all of the capital improvements projects for the City at our Property and Project Portal.
- Check for no-parking signs before parking on Main Street. No parking signs will specify hours and dates when parking will be limited.
- Keep an eye on construction while driving. Pay attention, slow down, and move over to keep yourself and workers safe. Please be kind to our construction workers and contractors!
Questions?
Questions can be answered by the City’s project manager, Dan Todd at mainstimprovements@primeeng.com. You can also contact the City of Troy Engineering Department 937-339-2641.