The concrete curb and gutter crews completed the long sections remaining on the south side of W. Main Street this week. Full depth pavement removal is taking place in front of the gutter in preparation for full depth asphalt. Full depth asphalt should be completed next week prior to the Strawberry Festival.
The contractor will continue to work on the south side concrete ramps, sidewalks, and drive approaches now that the long sections of curb and gutter are in.
The north side streetscape is almost complete. Power washing and concrete sealing will be applied to the completed portions next week prior to the Festival, and are already underway. The remaining portion at N. Cherry Street will be done after the Troy Strawberry Festival so that walkways are safer for festival visitors.
Traffic signal and lighting crews will commence work as materials become available. These items have long lead times for production.
For more information, submit your question via email to: MainStImprovements@primeeng.com. Upcoming road closures can be viewed here.